Our construction is moving along on schedule!

I’m impressed with the quality of the work we’re getting done and how secure the new masonry demising walls are.

DSC01544
Outside facing south.
DSC01550
An interior unit with the demising walls up. The back wall needs to be enclosed between the beams. The bathroom and shop sink need to go in as well as the electrical panel and motorized garage door.

DSC01552

An exterior unit with the demising walls up. The back wall needs to be enclosed between the beams. You can see the window for the mezzanine, which will be installed in this unit. The bathroom and shop sink need to go in as well as the electrical panel and motorized garage door.